Scope of work:
Widening of the existing highway of an approximate length of 33 km and the upgrading of the existing intersection of Al Barsha Road. South with Emirates Road into grade separated interchange (J1), in addition to the construction of two new interchanges (J1A & J3) to provide access. The work also includes the provision of street lighting services to the proposed roadway facilities, crossing ducts for different utilities, and the relocation and/or protection of existing services.
Client: RTA
Consultant: Wilbur Smith Associates in association with Al Turath Engineering Consultants
Year of Award: 2008
Contract Duration: 87 months
Contract Value: AED 940 Milion